The following is the schedule for New Castle Paving as work continues on the City of Watervliet’s 2025 Seasonal Paving Project.
- Monday-Tuesday – Pour Ramps on 11th and 23rd , ramp excavation and removal on 7th, 15th
- Wednesday – Mill 23rd Street
- Thursday – Pave 23rd Street, Finish milling 23rd street, mill 9th Avenue, 11th Avenue and Railroad alleys from 24th to 25th and 23d to 9th
- Friday – Pave Remainder of 23rd Street, 9th Ave, 11th Avenue, Railroad Alleys between 24th and 25th and 23rd and 9th, continue excavation and ramp removal on 7th/15th and start getting into ramp removal on 7th, 5th or 4th.
The city will continue to provide project updates each week and any other times deemed necessary.